• Reconstruction of the restroom in the Student Center 2nd floor women’s locker room continues.
  • We will be reviewing the first “draft” of furniture layout for the new Calice Advanced Manufacturing Center this week including in the Atrium/Connector, where we hope to provide some type of “coffee shop” atmosphere.
  • Window installation throughout the new Calice Advanced Manufacturing Center continues.
  • Masonry work for the new elevator in Calice continues.
  • Ceiling grid and interior light installation continues.
  • Tile work continues in the bathrooms.
  • The interior brick wall on the south side of the Connector is complete.
  • Exterior brick work continues. Slab preparation (subbase work) continues for the radiant floor in the Connector.

NOTE:  We will once again be conducting “walk throughs” of the new Calice Advanced Manufacturing Center beginning this Thursday at 11 a.m. (and for the next three Thursdays). Please contact Pati Collins at ext 5007 or at collinspj@sunybroome.edu to confirm your attendance. Please meet at the construction trailer before the walk-through. Everyone should check it out!

As always, if anyone has any questions, please contact David Ligeikis at 607 765-9710.

Under Construction logo