- Roof decking has been placed on the Connector roof and entrance-way canopies between the new Calice Advanced Manufacturing Center and the Business Building.
- Demolition continues between the AT Building and the new Calice Center. Please advise if the noise created by this demolition causes disruption to classes in the AT Building.
- Excavation for the new elevator in Calice continues.
- Installation of duct work and exterior brick work continues.
- Interior priming and painting continues.
If anyone has any questions, please do not hesitate to contact David Ligeikis at (607) 765-9710.