Calice Advanced Manufacturing Center

  • Blacktop paving on the west and north sides of Calice has been completed (pavers to follow)
  • Installation of the epoxy floor in both the Fermentation Lab and Food Processing Lab has been completed
  • The ceiling grid is 90% complete in the first floor corridor and lighting has been mounted
  • VCT (vinyl) flooring and painting has been completed in the basement storage room (soon to become the new photography lab)
  • HVAC start up and balancing will take place on June 29, 2018
  • Surface mounted lighting has been placed under the overhang within the Connector
  • Construction of the east vestibule for the Connector has started
  • The new elevator has been delivered and installation will commence
  • Door auto operators have been installed
  • Glass has been installed at the sidelights on the first level
  • Commissioning of the photovoltaic system has taken place
  • The Fire Department connection is in place

Carnegie Culinary Center

  • The basement concrete floor has been removed
  • Excavation exposing the foundation is in progress (for underpinning construction)
  • The rear addition to the Library has been completely removed
  • Overall demolition is approximately 90% complete
  • Electrical rough-ins (ceilings and walls) is underway