Calice Advanced Manufacturing Center
-
Concrete sidewalk and curb installation work continues
-
Painting has been completed in the Connector and lighting has been installed
-
The ceiling grid on the first floor is nearing completion
-
Lab equipment is being moved back into Calice
-
VCT flooring on the first floor is approximately 75% complete, the second floor is approximately 95% complete
-
Work continues on door frames and door fronts
Carnegie Culinary Center
-
Both interior and exterior demolition continues
-
Windows have been measured for fabricationAs always, if anyone has any questions, please contact David Ligeikis at (607) 765-9710.