During the week of Jan. 15:

  • Plumbing and electrical “rough ins” continue on the first floor of the Mechanical Building/Calice Center.
  • Electric/power pathways are being brought to the first floor labs.
  • Taping/finishing/priming of sheet rock continues, especially in the corridors.
  • Construction of door frames continues throughout the building.
  • Interior block work continues in the west end of the building (in the Fermentation Science Lab and the Food Processing Lab).
  • Demolition of the handicapped access ramp between the AT Building and the new Calice Advanced Manufacturing Center continues.
PLEASE ALSO NOTE:  The Carnegie Library Culinary Arts Center project will be advertised for bid on Thursday, January 18, 2018. Bid packages are due on February 13, 2018 ,and will be opened the same day in the Events Room in the SUNY Broome Ice Center.
If anyone has any questions, please contact David Ligeikis at  607-765-9710