On-campus construction activities for the week of Nov. 6

Looking for information specific to the renovation of the Mechanical Building? We now have a dedicated website. Click here periodically for ongoing updates to the project, including the weekly construction update. As always, make sure to follow all signage and safety precautions in affected areas.

During the week of Nov. 6:
  • Interior masonry block wall installation will continue in the new Calice Advanced Manufacturing Center.
  • Mechanical, Electrical and Plumbing (MEP) “rough ins” will continue.
  • Weatherproofing of the exterior walls will begin this week.
  • Any remaining interior demolition work will continue.
As always, if anyone has any questions, please contact David Ligeikis at 765-9710.