On-campus construction activities for the week of Nov. 20

Under Construction logoLooking for information specific to the renovation of the Mechanical Building? We now have a dedicated website. Click here periodically for ongoing updates to the project, including the weekly construction update. As always, make sure to follow all signage and safety precautions in affected areas.

  • Piping from the geothermal field will be brought into the new Calice Advanced Manufacturing Center at the northwest corner of the building.
  • Weatherproofing of the external walls will continue (sealing of the joints and application to the exterior walls).
  • Wall framing in the second floor office suite is nearing completion.
  • Approximately 75% of the heat pumps have been installed.
  • Asbestos abatement in the building has been completed.
  • Corridor framing will begin on the second floor.
  • The mounts for the plumbing fixtures in the restrooms will be tested.
  • Electrical “rough ins” are nearly 75% complete.
  • Some steel erection for the connector/atrium should begin later this week.
If anyone has any questions, please contact David Ligeikis at 765-9710.