On-campus construction activities for the week of Nov. 13

Under Construction logoLooking for information specific to the renovation of the Mechanical Building? We now have a dedicated website. Click here periodically for ongoing updates to the project, including the weekly construction update. As always, make sure to follow all signage and safety precautions in affected areas.

During the week of Nov. 13:
  • Placement of EDPM (rubber membrane) will begin in the old Mechanical Building crawl spaces.
  • Excavation and trenching for the permanent power run between the Business Building and the New Calice Advanced Manufacturing Center will begin.
  • Overhead rough-ins for electrical will continue on the first floor.
  • Framing of the new walls in the second floor office suite will begin.
  • Hanging of the geothermal loop piping at the west end of the building will continue.
  • Heating/cooling units continue to be placed throughout the building.
  • Plumbing work continues on both the first and second floor bathrooms.
  • Application of the exterior weatherproofing membrane will begin this week.
  • Interior block installation continues.
  • Application of spray foam insulation continues on the second floor.
If anyone has any questions, please do not hesitate to contacts David Ligeikis at 607 765-9710.