• Asbestos removal/abatement work has been completed on the second floor and is nearing completion on the first floor of the Calice Center.
  • Now that the asbestos work is completed on the second floor, final painting, final placement of ceiling tiles and the hanging of doors has begun.
  • Insulating of pipes is continuing.
  • Sprinkler system piping in Calice continues.
  • Installation of the metal panels in the Connector area continues.
  • Framing of the east curtain wall is nearing completion (window installation to follow).
Other on-campus activity
  • The wall pads in the West Gym have been installed and finish painting completed.
  • Spring cleanup across campus continues.