• Tile/grout work continues in the first floor bathrooms.of the new Calice Advanced Manufacturing Center.
  • Painting (finish coats) are being applied on the first floor.
  • Data cable is being pulled on the first floor.
  • Wiring of the fire alarm panel has begun.
  • Sanitary piping is being installed in the building’s crawl space.
  • Elevator block work is approaching the second floor. We expect to cut through the second story floor sometime this week.
  • Door and window frame installation is nearing completion.