Calice Advanced Manufacturing Center
-
Shipments of both casework and fire-rated glass are arriving on site.
-
Our HVAC contractor will be commencing start-ups of the HVAC equipment.
-
Our electrical contractor will be starting the commissioning of lighting and fixtures.
-
Work has begun/is continuing in the data closets.
-
Connector curtain wall windows (for the east and west curtain walls) will be delivered on Thursday. Installation should take approximately two days.
-
Installation of the exterior metal panels continues.
-
Final grading (sub base) for paver installation is nearing completion.
-
The south entrance canopy has been completed (with the signed steel beam from the “topping off” event very visible).
-
Sidewalk construction and final grading/seeding of the Quad between Calice and the Natural Science Center has been completed.
-
VCT (floor tile) installation continues.
Culinary Arts Center (Carnegie)
- The construction fence is in place.
- The remaining asbestos abatement work is nearly complete. (All windows have been removed.)
- Interior demolition (both general construction and electrical) has begun.
- Temporary power panels have been set (awaiting NYSEG).
- Interior finish wood has been salvaged.
As always, if anyone has any questions, please do not hesitate to contact David Ligeikis at 607-765-9710.