On-campus construction activities for the week of June 11

Work has begun at the former Carnegie Library site in Binghamton.

Work has begun at the former Carnegie Library site in Binghamton.

Calice Advanced Manufacturing Center

  • VCT (floor tile) installation continues in the classrooms/corridors
  • Exterior concrete sidewalk/sub base work (pavers) continues
  • Light pole bases are scheduled for delivery this week
  • All exterior door frames should be set this week
  • All windows have been installed in the Connector curtain walls
  • Whiteboards are being installed in classrooms/labs
  • The first floor ceiling grid is nearing completion
  • Work on the terrazzo floor in the Connector should begin next week

Carnegie Culinary Arts Center

  • The project’s construction field office has been established at 95 Court Street in downtown Binghamton
  • All remaining asbestos abatement work has been completed (windows, roof, caulking, doors)
  • Temporary water and power (electric) to the site has been established
  • Interior demolition work continues
  • Meetings have been held to discuss underpinning construction (including some preliminary excavation)
As always, if anyone has any questions, please contact David Ligeikis at (607) 765-9710