Under Construction logoThe following construction activities are ongoing this week. Please be careful in affected areas and follow posted signage.
  • Electric/power pathways continue to be brought to the first floor labs in Calice.
  • The power shutdown of Business, Calice and the Annex which was scheduled for this Saturday, January 27, 2018 is now being postponed until a later date.
  • Framing for sheet rock continues in the first floor corridor.
  • Final painting on the second floor may begin this week.
  • Underpinning and excavation continue in the basement of Calice for the new elevator.
  • Once the interior block work is completed at the west end of the building, brick installation will restart on the building’s exterior.
  • Focus will soon turn toward work on the Connector/Atrium between Calice and Business.
  • Executive Council will tour the project site on Tuesday, January 22nd at 11 a.m.
As always, if anyone has any questions, please do not hesitate to contact David Ligeikis at 607 765-9710.