• The fire hydrants in front of the Wales Building and on the south side of the new Calice Center will be replaced this week.
  • New LED lighting will be installed in the fitness/cardio room, the weight room and the dance studio in the Student Center.
  • Concrete demolition will restart between the Calice Center and the AT Building as well as between the Calice Center and the Business Building.
  • Installation of electrical fixtures continues on the first and second floor of Calice.
  • The exterior south side brick wall of Calice has been completed. Work is beginning on the east side wall.
  • Bathroom tile work and painting continues on the first floor.
  • Installation of roofing insulation and vapor barrier continues in the Connector area.
  • The permanent power “switchover” for the new Calice Center is scheduled for 7 p.m. Wednesday, April 4, and should be completed by 7 a.m. Thursday, April 5.
  • First-floor floor leveling prep work continues.
  • The elevator shaft has “broken” through the second floor ceiling to the roof of Calice.
As always, if anyone has any questions, please contact David Ligeikis at 607 765-9710.