Construction Activities for the Week of July 24, 2017

  • Tree removals and landscape demolition will continue around the perimeter of the Mechanical Building
  • Hardscape removals  (brick pavers, etc.) will continue between the Business Building and the Mechanical Building
  • Selective demolition will begin on the 2nd floor, west side of the Mechanical Building
  • The attached campus map identifies the work zone area and the building access points which will remain open during construction.