The following construction activities are planned for the week of Aug. 28, 2017. Please pay attention to and abide by all construction signage in these areas.
  • Sidewalk and site lighting excavation will continue¬†around the perimeter of the old Mechanical Building.
  • Structural tie-in work and excavation (for the Calice Advanced Manufacturing/Business Building connector) will begin in the basement of the Business Building.
  • Well-drilling in the geothermal well field will continue. (Well-drilling hours have been adjusted to reduce noise impacts.)
  • Repair work and painting will continue on the Oz Winters SUNY Broome Tennis Courts.
  • Work for the Verizon Wireless project will focus primarily on work within building data closets (i.e., pulling wire and installing the repeaters).